We have reviewed this invoice and found the following differences:
Line 1, 60' articulating boom lift
Billed: $2,632.00. Should be: $1,776.00. Difference: $856.00.
Basis: Off-rent record of 2026-09-18, confirmation number OR-5531907. Called off rent on 2026-09-18: rent for the 8 days to that date is $1,776.00, $856.00 less than the amount billed ($2,632.00). Your agreement stops the rent at the off-rent call (Rental agreement, §5, dated 2026-03-02).
Line 2, 60' articulating boom lift
Billed: $3,852.00. Should be: $2,204.00. Difference: $1,648.00.
Basis: Rates printed on this invoice. Billed $3,852.00 for 9 days: $1,648.00 above the lowest combination of the rates printed on this invoice ($2,204.00).
Line 3, 32' rough-terrain scissor lift
Billed: $1,280.00. Should be: $1,120.00. Difference: $160.00.
Basis: Rental agreement, §4, dated 2026-03-02. Contract rates for class SL-32RT give $1,120.00 for 14 days: $160.00 less than the amount billed ($1,280.00).
Line 4, Rental protection plan
Billed: $1,164.60. Should be: $0.00. Difference: $1,164.60.
Basis: Written decline of the protection plan, dated 2026-03-02. A protection plan of $1,164.60 is charged; the plan was declined in writing with effect from 2026-03-02.
Line 5, Environmental fee
Billed: $194.10. Should be: $0.00. Difference: $194.10.
Basis: Rental agreement, §9, dated 2026-03-02. An environmental fee of $194.10 is charged; the agreement waives it.
Lines 6 and 7
Billed: $370.00. Should be: $0.00. Difference: $370.00.
Basis: Rental agreement, §6, dated 2026-03-02. Delivery and pickup of $370.00 are charged; the agreement includes them in the rent.
Line 8, Sales tax
Billed: $593.29. Should be: $0.00. Difference: $593.29.
Basis: Sales tax exemption certificate, dated 2026-03-05. Tax of $593.29 is charged; our exemption certificate, provided on 2026-03-05, covers all our purchases in TX on 2026-09-28.
Total difference: $4,198.60
Please issue a credit memo for $4,198.60 against invoice 4091-7733.
Thank you,Dana WhitcombKestrel Grading Co.